Icknield Way West (Puncture Alley) – Update

The contractors finished their remedial work last Wednesday, they then monitored cyclists on Thursday and Friday to see if there were any further puncture incidents.

 

The current situation is that the surface is being left and monitored for further reports of punctures. If there are still problems with punctures happening, please let the County Council know and also post them on the HarBUG forum.

Are cyclists using the path now? The problems with the surface has dented people’s confidence in the path but please let HarBUG know if you are still walking your cycle down the path instead of riding.

We need to get back to the Council in about a month to let them know how things are going, but sooner if the situation is still not acceptable.

Home Forums Icknield Way West (Puncture Alley) – Update

Viewing 7 reply threads
  • Author
    Posts
    • #2859
      admin
      Member

      Contractors have finished remedial work and now the path is being monitored for further puncture incidents.

      [See the full post at: Icknield Way West (Puncture Alley) – Update]

    • #2866
      Lewy
      Member

      Had a puncture last Tuesday evening as previously mentioned, bike was being repaired Thursday/Friday, Cycled to and from work using the path Monday/Tuesday this week with no punctures.

    • #2867
      numb-bum
      Member

      been cycling on it this week with no punctures, fingers crossed..

      Cheers Lewy for reporting the felled tree to OCC

    • #2874
      Anonymous
      Inactive

      I had to fix a puncture this morning. It was a piece of sharp flint.

      I have only used the ‘fixed’ track for 6 trips since the work to improve it.

      Sarah

    • #2875
      ezroller
      Member

      Would like to add that I have also been getting punctures on that stretch since the fix.

      Will start walking it again.

    • #2876
      Teatime
      Member

      I am going to try and notify the organisers of Uptonogood, an mtb event this summer, that will mean potentially several hundred riders using this stretch. With probable ensuing puncture mayhem!. I think now that flint splinters have been liberally distributed across and beside the path, this stretch will remain a problem for riders for many months if not years.

    • #2879
      Lewy
      Member

      I must be one of the lucky ones, I have been cycling across puncture alley since the fix and have only had one puncture, I think it may be a bit of a lottery and will be for a number of months to come!

    • #2894
      Lewy
      Member

      I spoke too soon…not sure if it’s the wet weather but have had two punctures in two days immediately after crossing puncture alley, anyone else?!